Eight deposits and four ways to trace the ramp
How much does a mine's cost change depending on how its ramp is traced?
In six of eight deposits, the calculated ramp comes out cheaper than the hand-drawn one. It saves up to 18%. In the other two, the hand-drawn spiral wins.
We measured it with one yardstick and the same prices for every ramp, and everything is open so you can check it with your own ramp.
What came out
- 6 of 8In six of the eight deposits the fine tracer ramp comes out cheaper than the best hand-drawn one. In the other two, the hand-drawn spiral wins.
- 18%That is the most the fine tracer saves against the best hand-drawn ramp, on one of the deposits.
- 0.3%That is the largest difference with which the yardstick reproduced the lengths of the three designs of a published case.
The percentages are on the cost of ramp, crosscuts, contingency and haulage over the life of the mine, undiscounted.
On the six-ramp deposit, the two best ramps tie in cost, at 49.23 and 49.25 million USD. Time separates them. One reaches first ore 193 days earlier, and that is worth 15.1 million in present value. See the six ramps
The figures are calculated with the starting prices, the same as on both pages. On each page you can move them and everything is recalculated.
What is here
Six ramps for one deposit
Six possible ramps for the same orebody, costed item by item, and a cascade that explains why one costs more than another.Test bench
The ways to trace the ramp, side by side on each deposit and measured with the same yardstick. There you see where each one wins and why.Your method
Bring the points of your ramp and measure it with the same rules and the same prices. Nothing leaves your browser.
How it was done
- 1
One yardstick
A single measurer and a single costing were built, the same for every ramp. The measurer checks grade, curves, straights, standoff and levels, and the costing adds ramp, crosscuts, contingency and haulage.
See how it is measured - 2
Tested before use
The yardstick was tested against a published case and against a ramp that was built. It reproduced the published lengths within 0.3% and the built ramp to the meter.
See the test - 3
Every way on every deposit
four ways to trace the ramp were run on eight deposits. There are five invented ones, the six-ramp deposit and two transformed real mines with invented names.
See the deposits - 4
The stress test
Of 60 new variants, 33 turned out to be valid deposits. On those, the hand-drawn spiral solved 33, the hand-drawn switchback 33, the fast tracer 31 and the fine tracer 27, with no code changed between the first run and the last.
See the stress test - 5
All open
Each deposit's data downloads complete, and anyone can bring their ramp and measure it on the same field.
See the data
What it is not
- It leaves out ventilation, detailed geotechnics, drainage and the construction sequence.
- Of the eight deposits, five are invented and one is the six-ramp one. The other two come from real mines, rebuilt from public reports, rotated, scaled and given invented names.
- Grade is constant within each body.
- The fine tracer does not go around obstacles, and that is why there are cases it does not solve.
- The starting prices are public or estimated. With the prices of your own site the result changes.
What we ask of you
- At your site, are the accesses on each level fixed before the ramp is traced, or is the ramp traced first and the crosscuts adjusted?
- What level spacing and what radius do you use? How much a method that passes through the accesses stretches depends on that relation.
- Would you like to measure your tracer on these deposits? Write to us and tell us in what format you would like the input data.